Construction Phases
This page was translated from German using artificial intelligence. The translation may contain errors or inaccuracies. In case of doubt, the German original version prevails.
The district council has decided to implement only one construction phase (orange marking). This limits the construction project to the absolutely necessary scope. Further construction phases (green and blue markings) are currently not under consideration.
The construction phase to be realized corresponds to 60 percent of the total space requirement of 9,200 m² program area. The construction phase is designed in such a way that the additional construction phases could still be implemented at a later date.
One Construction Phase Will Be Implemented:
One Construction Phase Will Be Implemented:
This construction phase is the most important step towards centralization.
It includes the building section along "Moltkestraße" and "Am Wiedenhof."
The old buildings north of the district hall will initially remain.
Administrative spaces with modern workplaces, a central citizen service area, barrier-free access, and modern technology will be created.
The construction is scheduled to begin in October 2027, with the first phase expected to be completed by October 2030.
Important for you: During the construction period, the district administration will remain accessible. Transitional solutions will ensure the usual citizen services.
Modern and Adaptable Workplaces
Modern and Adaptable Workplaces
As part of the centralization, spaces for flexible open office use and double offices with open building technology will be created. Meeting rooms will be designed to be versatile through movable room modules.
Sustainability and Energy Supply
Sustainability and Energy Supply
The sealing of surfaces is to be reduced. For this purpose, green spaces on roofs (retention roofs) are planned. Electricity is to be generated using a photovoltaic system.
Centralization at the New Location
The following organizational units are to be considered:
- District Youth Office (currently residential building at Am Wiedenhof 5)
- District Youth Office (currently residential building at Am Wiedenhof 15)
- District Youth Office (currently Moltkestraße 24)
- District Youth Office (currently Hindenburgstraße 24)
- District Youth Office (currently La Roche-Sur-Yon Str. 18)
- School Psychological Service (currently Hindenburgstraße 21-25)
- State School Office (currently Industriestraße 2)
- Municipal Integration Center (currently Schützenstraße 13)
- Office for Planning, Development, and Mobility, Economic Development, Oberbergische Development Company, Project Agency (currently Karlstraße 14-16)
- Office for Real Estate Management (currently Wilhelm-Breckow-Allee 15)
- Staff Council (currently Bismarckstraße 9a)
- Main Office, Department of Information and Communication Technology (currently District Hall Moltkestraße 42)
Additionally, the following organizational units are to return to the Moltkestraße location complex through optimized desk sharing and the consolidation of the service area for citizens:
- Municipal Supervision, Specialist Office for Civic Engagement and Volunteering (currently Bismarckstraße 9a)
- Legal Office (currently Moltkestraße 38)
The following organizational units cannot be accommodated at the Moltkestraße location complex if only the first construction phase is implemented:
- District Regulatory Office, Departments of General Hazard Prevention and Supervision and Residence and Citizenship
- Veterinary and Food Surveillance Office
- Office for Geoinformation and Land Registry
- Audit Office
- Rescue Service Office (Administration)
Already housed in their own premises are:
- the district-owned schools
- the Oberberg Adult Education Center
- the AGewiS
- the Road Traffic Office
- the Cultural Office/Schloss Homburg
- the Office for Fire, Civil, and Disaster Protection